- bond claim
- mechanics lien
- payment bond
- construction payment
Bond Claims vs. Mechanics Liens: Which One Do You Need?
The state rules in this article were checked on September 18, 2026 against LienShield's state lien guides, which cite each statute. Laws change, so follow the links to the current guide for your state.
You did the work. You bought the materials. And now someone is not paying. You know you have legal options, but should you file a mechanics lien, make a bond claim, or both? These two payment protection tools serve similar purposes but work in fundamentally different ways. Choosing the wrong one can cost you time and money. Choosing the right one can get you paid.
What Is a Mechanics Lien?
A mechanics lien is a legal claim you file against a property. When you improve a property through labor or materials and do not get paid, the lien gives you a security interest in that property. The property owner cannot sell or refinance until your lien is resolved.
Mechanics liens are available on most private construction projects. They are powerful because they create direct pressure on the property owner, even if your contract was with a general contractor or another subcontractor.
Key characteristics of mechanics liens:
- Filed against the property itself, not against a person or company
- Mechanics lien laws exist in all 50 states, though a few (Hawaii, Maryland and New Hampshire among them) create the lien only through a court action
- Subject to strict deadlines that vary by state (commonly 60 to 120 days from your last work)
- Require preliminary notices in many states
- Can lead to foreclosure of the property if unpaid
- Must typically be enforced through a lawsuit within a set timeframe
What Is a Bond Claim?
A bond claim is a claim against a surety bond. On many public construction projects and some large private projects, the general contractor is required to purchase a payment bond. This bond is essentially an insurance policy that guarantees subcontractors and suppliers will be paid.
When you are not paid on a bonded project, you file a claim against the bond rather than against the property. The surety company that issued the bond investigates the claim and pays valid claims up to the bond amount.
Key characteristics of bond claims:
- Filed against the surety bond, not the property
- Required on most public projects (federal, state, and local government)
- Available on private projects only if the owner required a payment bond
- Subject to their own notice and filing deadlines
- Do not create a lien on the property
- The surety company investigates and pays valid claims
The Critical Difference: Public vs. Private Projects
Here is the most important rule to remember: in most states you cannot file a mechanics lien on a public project. Government-owned properties like schools, roads, courthouses, and public utilities are generally protected from liens. This is why payment bonds exist on public projects. They replace the lien right you would have on a private job.
On a private project, you typically have the right to file a mechanics lien. You may also have the right to make a bond claim if the project has a payment bond, though most private residential and small commercial projects do not.
On a public project, a bond claim is usually your only option for payment protection. The federal Miller Act requires a payment bond on federal construction contracts over $100,000 (40 U.S.C. § 3131). Most states have similar "Little Miller Acts" for state and local projects, each with its own notice and suit deadlines.
Comparing the Two: Key Differences
Who Pays?
Mechanics lien: The property owner is ultimately responsible. Even if the GC failed to pay you, the property owner's property is encumbered. This creates pressure on the owner to resolve the payment dispute.
Bond claim: The surety company pays. The surety then seeks reimbursement from the contractor who failed to pay you. The property owner is typically not involved.
Deadlines
Both tools have strict deadlines, but they differ:
Mechanics lien deadlines vary dramatically by state: from 30 days for Alabama laborers to 8 months on private work in New York, and in some states the clock runs from completion of the whole project. Many states also require preliminary notices within a set number of days from your first day of work.
Bond claim deadlines are set by the applicable statute and the bond. Under the federal Miller Act, a claimant who did not contract directly with the prime contractor must give written notice within 90 days of its last work, and every claimant must sue within one year of its last work (40 U.S.C. § 3133(b)). State bond claim deadlines vary.
Enforcement
Mechanics lien enforcement requires filing a lawsuit to foreclose on the property within the state's deadline, which ranges from 90 days after recording in California to a year or more in many states. If you do not enforce within the deadline, the lien expires.
Bond claim enforcement involves filing a claim with the surety company. If the surety denies your claim, you can file a lawsuit against the surety, within the statute's deadline. The process can be faster than lien foreclosure because the surety has an incentive to resolve valid claims.
Notice Requirements
Mechanics liens often require a preliminary notice early in the project. If you skip the preliminary notice in a state that requires one, you may lose your lien rights entirely.
Bond claims also require notice, but the rules depend on the bond terms, the applicable statute, and whether you have a direct contract with the bonded contractor or are a lower-tier subcontractor.
When to Use Each
Use a mechanics lien when:
- The project is on private property
- You want maximum leverage against the property owner
- There is no payment bond on the project
- You have met all notice requirements for your state
Use a bond claim when:
- The project is a public (government) project
- The project has a payment bond
- You want to avoid a lien foreclosure lawsuit
- The property owner is not the party who owes you
Use both when:
- The private project has a payment bond
- You want to maximize your payment protection
- State law allows both remedies simultaneously
Do Not Miss Your Deadlines
Whether you choose a mechanics lien, a bond claim, or both, the deadlines are non-negotiable. Miss a preliminary notice by one day, and you could lose your rights entirely. Miss a filing deadline, and your claim expires.
LienShield tracks lien deadlines for the 49 US jurisdictions it supports and reminds your team before they close. Enter your project and it calculates the dates it can, each tied to the statute, so they are in front of you instead of buried in a law book. Each state guide also covers the public-works bond rules.
Not legal advice. LienShield is a document preparation service, not a law firm. This is general information about how lien rules work; statutes differ by state, project type and your role on the job. Confirm dates and requirements for your project with a licensed attorney or the recording office before you rely on them.