Missouri is unusual in three ways. Your lien gets filed with the clerk of the circuit court of the county where the property sits — not the recorder of deeds, which is where most states send it (Sec. 429.080). Almost everyone gets six months from their own last day of work to file, but an outfit that rents equipment to others gets only 60 days from the day the equipment came off the site (Sec. 429.080). And Missouri has four completely different pre-lien notices that are not interchangeable: the original contractor owes one document, everybody below them owes a different one, equipment lessors owe a third, and on residential property a recorded notice of rights can be the only thing standing between you and a total forfeiture. Serving the wrong one is the same as serving none.

Your role on the job

The deadlines and steps change with your role. Pick yours.

At a glance

Subcontractor on a commercial job in Missouri

Preliminary notice

At least 10 days before you file the lien

It must state the amount then due, so serve it again if that amount changes.

Mo. Rev. Stat. § 429.100(opens the statute in a new tab)
Notice of intent
File the lien

180 days after you last furnish labor or materials

Mo. Rev. Stat. § 429.080(opens the statute in a new tab)
Someone else can shorten this window
File suit to enforce

The rules as the statute states them. LienShield turns them into dates from your project's work dates. Residential and commercial are the private-project rules; public jobs follow separate bond rules, covered in the steps below.

Step by step

10 steps for a subcontractor in Missouri.

  1. Step 1: Find out if the job is public and bonded before you rely on lien rights

    Before you start work, and definitely before you spend money preparing a lien.

    On a public works job where the public entity required a payment bond, subcontractors and suppliers have no mechanics lien at all. A lien filed anyway is void by statute and gets thrown out summarily. Your money comes from the bond instead. Missouri public entities have to require a bond on public works contracts estimated to cost more than $50,000.

    Where it goes
    The public body that awarded the contract — city, county, school district, state agency.
    How
    Ask the public entity or the general contractor for a copy of the payment bond and the bond number. Get it in writing.
    Proof to keep
    A copy of the bond, and the email or letter you sent asking for it.

    If you miss it: You file a mechanics lien on a bonded public job and it is void, unenforceable and summarily discharged. You spend the filing money and the six months for nothing, and the real deadline you needed to hit was the bond notice.

  2. Step 2: On residential repair or remodel work, get a signed CONSENT OF OWNER

    The statute does not set a date. But a signed copy has to be attached when you record your lien claim, so you need it in hand before you file.

    If the job is the repair or remodeling of, or an addition to, owner-occupied residential property of four units or less, then nobody except the original contractor gets a lien unless an owner signed a Consent of Owner under a written contract. It has to be printed in ten-point bold type and signed separately from the Sec. 429.012 notice to owner. This does not apply to building the original residential unit itself, or to other improvements that are part of the original development.

    Where it goes
    Signed by an owner of the property. A signature from one owner binds the others.
    How
    A written document in ten-point bold type, signed by an owner, separate from any other notice, backed by a written contract in which an owner agreed to be liable for the costs.
    Proof to keep
    The original signed consent, plus the written contract it sits under. You will attach a copy to your recorded lien claim.
    What the document must contain
    • The heading CONSENT OF OWNER
    • The statutory language from Sec. 429.013.2: CONSENT IS HEREBY GIVEN FOR FILING OF MECHANIC'S LIENS BY ANY PERSON WHO SUPPLIES MATERIALS OR SERVICES FOR THE WORK DESCRIBED IN THIS CONTRACT ON THE PROPERTY ON WHICH IT IS LOCATED IF HE IS NOT PAID.
    • Printed in ten point bold type
    • Signed separately from the Sec. 429.012 notice
    • An owner's signature

    If you miss it: You have no lien, no matter how perfectly you do everything else. Sec. 429.013.3 makes attaching a signed consent a condition precedent. And under Sec. 429.013.4, if the homeowner paid the contractor in full, that full payment is a complete defense to your lien. Faking an owner's signature on one of these is a class D felony (Sec. 429.013.5).

  3. Step 3: On a residential job, watch the recorder for a notice of intended sale and record a NOTICE OF RIGHTS

    Not less than five calendar days before the intended closing date stated in the owner's recorded notice of intended sale. If that fifth day lands on a Saturday, Sunday or Missouri legal holiday, you get until the next day the recorder is open.

    This is the trap that wipes out whole claims in Missouri. On residential real property, if the owner records a notice of intended sale, every claimant who wants to keep lien rights has to record a notarized notice of rights with the recorder of deeds before the closing date stated in that notice. Miss it and you are deemed to waive and forfeit all lien rights — before your filing deadline has even run. The owner is required to record their notice at least 45 calendar days before the earliest date they intend to close, post a copy at the property, and give you a copy and the legal description within five days of your written request.

    Where it goes
    The office of the recorder of deeds for the county where the property is located. Note this is a different office from where your lien itself gets filed.
    How
    Record it. It has to be signed by someone authorized to sign for you, and that signature has to be notarized. The recorder indexes owners as grantors and claimants as grantees, and the owner's signature is not needed to record it.
    Proof to keep
    The file-stamped recorded copy. You have to attach a photocopy of it to your lien statement later.
    What the document must contain
    • Date of the document
    • Owner's name
    • Claimant's name and address
    • Legal description of the property
    • Name of the person contracting with the claimant for the work
    • Names of persons performing work for or supplying materials to the claimant
    • Notarized signature of a person authorized to sign for the claimant

    If you miss it: You waive and forfeit any right to assert a mechanics lien against that property (Sec. 429.016.6). And if you record it after the owner has already conveyed to a bona fide purchaser for value, it does not work at all — there is no relation back (Sec. 429.016.7).

  4. Step 4: Keep a running itemized account of exactly what you furnished

    Every week of the job. Start on day one.

    Your lien statement has to be a just and true account of what you are owed after all just credits have been given. Missouri takes that literally. The account you file has to be built from real records — dated, itemized, showing every payment and credit you received — because the account is the lien. A lump sum with no itemization, or an account that mixes in things that are not lienable, is a problem you cannot fix after you file.

    Where it goes
    Your own files. Nothing gets filed at this stage.
    How
    Keep dated daily tickets, delivery slips, invoices, change orders and a payment ledger showing credits applied.
    Proof to keep
    The contract or purchase order, every invoice, every delivery ticket, and a statement of account showing payments and credits.
    What the document must contain
    • Itemized amounts due, not a lump sum
    • All payments and credits already received, applied against the total
    • Only lienable work and material for this property
    • The first and last dates you furnished labor or material

    If you miss it: When you file, you will not be able to produce a just and true account after all just credits, and Missouri courts have treated a padded or lump-summed account as defeating the whole lien, not just the bad lines.

  5. Step 5: Serve the ten-day notice on the owner before you file

    At least ten days before you file the lien. It runs backward from your filing date, so if you plan to file on day 175, serve it by day 165.

    Everybody except the original contractor has to give the owner ten days' notice before the lien gets filed, saying how much is owed and who owes it. This is a separate document from anything the original contractor serves. If you contracted directly with the owner, this is not your notice — see the NOTICE TO OWNER step instead.

    Where it goes
    The owner, the owners, or the owner's agent.
    How
    Two ways only. By an officer authorized by law to serve process in civil actions — their official return on the notice is your proof. Or by any person who would be a competent witness, in which case that person has to verify the service by affidavit. If the owner is not a Missouri resident, has no agent in the county, is concealing themselves, has absconded, or is away from their usual place of abode, you can instead record the notice with the recorder of deeds for that county, and it has the same effect as service (Sec. 429.110).
    Proof to keep
    The officer's official return endorsed on the notice, or the process server's affidavit of service. If you recorded it under Sec. 429.110, the file-stamped recorded copy and the recording fee receipt.
    What the document must contain
    • The amount due
    • From whom it is due
    • Reference to the claim against the building or improvement

    If you miss it: The notice is a statutory precondition to your lien. Serve it late, serve it fewer than ten days out, or serve it by a method the statute does not allow, and you are defending the validity of your lien instead of collecting on it.

  6. Step 6: File your lien statement with the circuit clerk within six months

    Within six months after the indebtedness accrued, which is your own last day of furnishing labor or material on the job.

    This is the lien itself. You file a sworn, itemized account of what you are owed with the clerk of the circuit court. Missouri measures the six months from when your indebtedness accrued — your own last day of furnishing labor or material — not from when the overall project finished.

    Where it goes
    The clerk of the circuit court of the county where the property is located. Not the recorder of deeds. Filing at the recorder does not perfect your lien.
    How
    File it in person or by the county's accepted filing method, verified by oath. The account has to be sworn to by you or by some credible person on your behalf.
    Proof to keep
    The file-stamped copy from the circuit clerk showing the filing date. That date starts your six-month suit clock.
    What the document must contain
    • A just and true account of the demand due you, after all just credits have been given
    • A true description of the property, or close enough to identify it
    • The name of the owner or the contractor, or both, if known
    • Verification by the oath of yourself or some credible person for you

    If you miss it: You have no lien. The six-month period cannot be extended or waived by agreement.

  7. Step 7: On a residential job, attach the extra paperwork to the lien statement

    At the moment you file the lien statement.

    Residential filings carry a document package that commercial filings do not. If you recorded a notice of rights under Sec. 429.016, a file-stamped photocopy of it goes in with your lien statement. And on an owner-occupied repair or remodel of four units or less, a copy of the signed Consent of Owner has to be attached to the recording of your lien claim.

    Where it goes
    The clerk of the circuit court, with the lien statement.
    How
    Attach copies to the lien statement you file.
    Proof to keep
    The complete file-stamped filing package as accepted by the clerk.
    What the document must contain
    • A photocopy of the file-stamped notice of rights and any renewals
    • The name and address of the person or entity you contracted with
    • A copy of any contract, purchase order or proposal — or, if there was no written agreement, a general description of the scope of work
    • All invoices you submitted for your work on the property
    • An accurate statement of account showing all payments and credits
    • The last date you performed any work or labor on the property
    • On owner-occupied residential repair, remodel or addition of four units or less: a copy of the Consent of Owner signed by an owner (Sec. 429.013.3)

    If you miss it: The Consent of Owner attachment is a condition precedent under Sec. 429.013.3 — without it there is no lien for anyone other than the original contractor. The Sec. 429.016.15 documents are what the statute says the claimant shall provide with the lien statement, so a short package invites a challenge you did not need to face.

  8. Step 8: Sue within six months of filing, or the lien stops existing

    Within six months after the date you filed the lien. Note that this clock starts at filing, not at your last day of work.

    Filing the lien is not the end. Missouri gives you six months from the filing date to commence an action on it, and the statute says no lien continues to exist beyond six months from filing unless an action is instituted within that time. The lien does not just become unenforceable — it ceases to exist.

    Where it goes
    Circuit court. The parties to the contract have to be made parties to the suit; anyone else interested in the property may be made a party, and anyone not made a party is not bound by the result (Sec. 429.190).
    How
    Commence a civil action to enforce the lien. Pleadings run as in other civil cases (Sec. 429.180). If an equitable mechanics lien action is already pending, an answer, other pleading, motion, or entry of appearance followed by pleading, filed within your six months, counts as commencing your action (Sec. 429.310).
    Proof to keep
    The file-stamped petition or pleading and the case number, dated inside the six months.

    If you miss it: The lien ceases to exist. You may still have a breach of contract claim against whoever owes you, but the security interest in the property is gone.

  9. Step 9: Watch for an equitable mechanics lien action — it takes over your case

    Any time after a lien statement has been filed. It is not on your schedule — check the circuit court docket for the property after you file.

    This is the lever the other side can pull. Any lien claimant after their statement is filed, and also any owner, lessee, mortgagee or other encumbrance holder, can start an equitable action to sort out everyone's liens at once. Once that action is brought, it is exclusive of other remedies for enforcing mechanics liens, all other pending mechanics lien suits are stayed and not further prosecuted, and no new separate lien suit can be filed. You do not get to run your own case anymore — you have to appear in theirs, and you still have to do it inside your own six months from filing.

    Where it goes
    The circuit court where the equitable action is pending.
    How
    Appear in the equitable action and plead. An answer, other pleading, motion, or entry of appearance followed by pleading, filed within six months of your own lien filing, is what counts as commencement by you.
    Proof to keep
    Your file-stamped answer or pleading in the equitable action, dated inside your six months.

    If you miss it: Your own separate suit is stayed and goes nowhere, and if you did not plead or appear in the equitable action within six months of filing your lien, your lien ceases to exist under Sec. 429.170. Being named by someone else is not the same as commencing your own action.

  10. Step 10: File an acknowledgment of satisfaction once you are paid

    Within ten days after payment and a request to enter satisfaction.

    When the debt secured by the lien is paid or satisfied, you have to file an acknowledgment of that satisfaction if you are asked to. It is a small step with a real penalty attached.

    Where it goes
    The clerk of the circuit court.
    How
    File a written acknowledgment of satisfaction. If your lien covered multiple lots or tracts and you are releasing only some of them, Sec. 429.032 sets out a Partial Release of Mechanic's Lien form with notary blocks for individuals and for corporations.
    Proof to keep
    The file-stamped satisfaction, and the date you received payment and the request.

    If you miss it: Refuse to enter satisfaction within ten days after payment and request and you are liable to any person injured for the amount of the injury plus the cost of suit.

Who can claim a lien in Missouri

Who has a lien in Missouri

  • Has a lien: Anyone who performs work or labor on the property, or furnishes material, fixtures, engines, boilers or machinery for a building, erection or improvement, under a contract with the owner, the owner's agent or trustee, or with a contractor or subcontractor (Sec. 429.010.1).
  • Has a lien: People who furnish landscaping goods or services, or install outdoor irrigation systems (Sec. 429.010.1).
  • Has a lien: Companies that rent machinery or equipment to others — but only on commercial property, only if the claim exceeds $5,000, and only if they gave the owner written notice within 15 business days of first use (Sec. 429.010.2).
  • Has a lien: Contractors who use rented machinery or equipment in performing their own work. The Sec. 429.010.2 gates and the 60-day rule do not apply to you — you are on the ordinary six-month track (Sec. 429.010.2, Sec. 429.080).
  • Has a lien: Registered architects, professional engineers, landscape architects and land surveyors, and corporations registered to practice those professions (Sec. 429.015.1). If you contracted directly with the owner or lessee, you can lien even if construction never started, provided your agreement is in writing (Sec. 429.015.5, .8).
  • Has a lien: On a public works job covered by a Sec. 107.170 payment bond: no subcontractor or supplier has a mechanics lien. The bond is the remedy (Sec. 107.170.8).

Who does not have a lien in Missouri

  • No lien: On owner-occupied residential property of four units or less that is being repaired, remodeled or added to: nobody except the original contractor has a lien at all unless an owner signed a Consent of Owner (Sec. 429.013.2).

Deadlines that can be cut short

In Missouri, these events can start a shorter clock or end a window early. Most are in someone else's hands, and you may not hear about them for days, so watch your mail and the county records.

  • The OWNER (or the owner's designated agent) records a notice of intended sale of residential real property with the recorder of deeds under § 429.016.11(1)

    Notice deadline: 40-day window

    Mo. Rev. Stat. §§ 429.016.3, 429.016.6, 429.016.11(1)
  • The OWNER conveys residential real property to a bona fide purchaser for value before the claimant has recorded its § 429.016 notice of rights

    Lien filing deadline: can end when this happens

    Mo. Rev. Stat. §§ 429.016.7, 429.016.6
  • The contractor furnishes a § 107.170 payment bond on a public works project (the public entity must require one where the cost is estimated to exceed $50,000)

    Lien filing deadline: can end when this happens

    Mo. Rev. Stat. § 107.170.8
  • On owner-occupied residential repair/remodel/addition of four units or less, the owner PAYS the original contractor in full and never signed a § 429.013 consent of owner

    Lien filing deadline: can end when this happens

    Mo. Rev. Stat. §§ 429.013.2, 429.013.3, 429.013.4

Where you file

Office
Clerk of the Circuit Court
Recording fee
$5
Notarization
Required
Sworn or verified
Affidavit
How it is served
Personal service
Copies
1

Fees and office procedures change; confirm them with the recording office before you file.

What trips people up in Missouri

  • Filing at the recorder of deeds. Sec. 429.080 sends the lien statement to the clerk of the circuit court. Missouri is one of the few states that does it this way, and a filing at the recorder does not perfect anything. Confusing, because two other Missouri filings — the Sec. 429.016 notice of rights and the Sec. 429.110 recording for an absent owner — do go to the recorder.
  • An original contractor serving the ten-day notice instead of the NOTICE TO OWNER. Sec. 429.100 opens with 'Every person except the original contractor.' It is not your notice. Yours is the ten-point bold Sec. 429.012 disclosure, due before you collect any money, and Sec. 429.012.2 makes it a condition precedent to your lien existing at all.
  • Serving the ten-day notice by certified mail. Sec. 429.100 allows service by an officer authorized to serve civil process, whose official return is the proof, or by any person competent to be a witness whose service is then verified by affidavit. Certified mail is not one of the listed methods.
  • Equipment lessors using the six-month deadline. Sec. 429.080 gives rental equipment rented to others 60 days from the date the last of the equipment was removed from the property. A lessor who waits for the six-month date is four months late, and the removal date is often later than the last invoiced rental day — measure from removal.
  • Equipment lessors assuming they have a lien. Sec. 429.010.2 means there is no rental lien on residential property at all, none for a claim of $5,000 or less, and none if the 15-business-day notice did not reach the owner after use began. Three gates, all three have to open.
  • Measuring six months from project completion. Sec. 429.080 runs from when your indebtedness accrued — your own last furnishing. A sub who finishes framing in March and waits for the building to top out in October is months out of time.
  • Treating six months as 180 days without checking the calendar. The statute says six months. Count the actual calendar date and file well before it; do not build a plan around a day count that may not line up with the month.
  • Skipping the Consent of Owner on a residential remodel. On repair, remodeling of, or an addition to owner-occupied residential property of four units or less, Sec. 429.013.2 gives nobody but the original contractor a lien without a ten-point bold consent signed by an owner, and Sec. 429.013.3 makes attaching it a condition precedent. Then Sec. 429.013.4 lets the homeowner defeat you outright by proving they paid the contractor in full.
  • Assuming the Consent of Owner rule covers new construction. It does not — Sec. 429.013.1 expressly excludes building or erecting the initial or original residential unit and improvements forming part of the original development. New residential construction runs on Sec. 429.016 instead. Getting the wrong one of these two regimes is the single most common residential error in Missouri.
  • Not watching the recorder of deeds on residential jobs. The owner can record a notice of intended sale and start a clock you never see. You then have until five calendar days before the stated closing date to record a notice of rights, and if you miss it you waive and forfeit all lien rights under Sec. 429.016.6 — regardless of how much time is left on your filing deadline. Recording it after conveyance to a bona fide purchaser is worthless (Sec. 429.016.7).
  • Assuming the notice of rights buys you time. It does not. Sec. 429.016.12 says recording it does not extend the Sec. 429.080 filing deadline. It does, however, relieve you of the Sec. 429.100 ten-day notice (Sec. 429.016.14).
  • Filing a mechanics lien on a bonded public works job. Sec. 107.170.8 makes it void, unenforceable and summarily discharged. Worse, a remote supplier who spends the season preparing a lien blows through the 90-day written notice to the contractor that was its only real remedy.
  • Filing a lump-sum or padded account. Sec. 429.080 requires a just and true account after all just credits. Missouri courts have treated an account that commingles non-lienable items or is stated as a lump sum as defeating the entire lien, not just the offending amounts.
  • Filing the lien and then waiting. The six-month enforcement clock in Sec. 429.170 starts on the filing date, and the lien ceases to exist at six months if no action is instituted. Being named as a defendant in someone else's equitable action does not commence your action — Sec. 429.310 requires you to answer, plead, move, or enter appearance and then plead, within your own six months.
  • Relying on older lien summaries. Plenty of secondary sources still print the pre-2005 Missouri rule giving laborers 60 days and subcontractors four months. Missouri's own Revisor page for Sec. 429.100 carries a 1964 annotation referring to 'the four-month provision of 429.080.' That is repealed law. The current Sec. 429.080, effective 28 August 2007, gives six months to original contractors, journeymen, day laborers and every other person alike.
  • Signing a lien waiver to win the job. Sec. 429.005 makes an agreement to waive lien rights, given in anticipation of and in consideration for the award of a contract, against public policy and unenforceable. But the same section leaves contractual provisions requiring lien waivers as a condition for payment perfectly valid — so the waiver you sign at each pay application is real.

After you file

  • Your six-month clock restarts. Sec. 429.170 gives you six months from the date you filed the lien to commence an action, and says no lien continues to exist beyond six months from filing unless an action is instituted within that time. Put the filing date and the six-month date on the wall.
  • Check the circuit court docket for the property periodically. Under Sec. 429.270, any lien claimant, or the owner, lessee, mortgagee or other encumbrance holder, can start an equitable action once a lien statement is on file. Once it is brought, Sec. 429.290 makes it exclusive of other remedies and Sec. 429.300 stays every other mechanics lien suit and bars new ones. You have to appear and plead in it.
  • Whatever route the case takes, you personally have to plead or appear inside your own six months. Sec. 429.310 counts an answer, other pleading, motion, or entry of appearance followed by pleading as commencement — but only if it lands within six months of your lien filing and the equitable action is still pending.
  • If you are the original contractor and a sub or supplier files a lien on your job, Sec. 429.140 requires you to defend any action brought on it at your own expense. Meanwhile the owner may withhold from you the amount the lien is filed for, deduct any judgment and costs from what they owe you, and if they already paid you in full, recover back from you what they had to pay out.
  • Your lien is preferred to encumbrances that attached to the building, improvement or ground after the commencement of the building or improvement (Sec. 429.060), and it reaches the whole tract the improvement sits on, but only to the extent of the right, title and interest the owner actually has in it (Sec. 429.030).
  • When you get paid, file an acknowledgment of satisfaction with the circuit clerk if you are asked to (Sec. 429.120). Refuse for more than ten days after payment and request and you are liable to anyone injured for their injury plus the cost of suit (Sec. 429.130).
  • On a bonded public works job, the bond is your remedy instead of a lien (Sec. 107.170.8). Sec. 107.170 does not itself state a deadline for suing on the bond, so that date has to come from the bond's own terms or from separate advice — do not assume it matches the lien timeline.

Where this comes from

Based on Mo. Rev. Stat. §§ 429.005 to 429.360; see also § 107.170 (public works payment bond) and 40 U.S.C. § 3133 (federal projects)(opens the statute in a new tab). Each step above links to the section it comes from.

Researched from the statute and independently cross-checked. Not yet reviewed by a licensed attorney. Last verified 2026-09-17.

This is general information about the lien process in this jurisdiction, not legal advice for your project. LienShield is a document preparation service, not a law firm. Verify with counsel before relying on any date or step.

Track your Missouri deadlines automatically

Enter the job once. LienShield works out every date in this guide for your role and reminds your team before each one closes.

Start free

All state guides