How to file a mechanics lien in Texas
Last verified 2026-09-17Researched and cross-checked; not yet reviewed by an attorney
Texas does not count days. Almost every Texas lien deadline is anchored to the 15th of a month, counted forward from the month you did the work — so the first thing you need is not a date, it is a calendar month. The second thing that makes Texas unusual: if you did not contract directly with the owner, you must send a separate notice for EVERY month you worked and were not paid. One notice at the end of the job does not protect the earlier months. Third, Texas runs on a residential/commercial split, and residential deadlines are one month shorter at every single stage. Get the project type wrong in the 'commercial' direction and every deadline you calculate is a month too late.
Your role on the job
The deadlines and steps change with your role. Pick yours.
At a glance
Subcontractor on a commercial job in Texas
- Preliminary notice
By the 15th day of the 3rd month after each month you furnish labor or materials
Tex. Prop. Code Sec. 53.056(a-1)(1)(opens the statute in a new tab)Called the Notice of Claim for Unpaid Labor or Materials.
A separate notice is due for each month of work.
- File the lien
By the 15th day of the 4th month after the month you last furnished labor or materials
Tex. Prop. Code Sec. 53.052(a)(1)(opens the statute in a new tab)Retainage: By the 15th day of the 3rd month after the month the original contract was completed, terminated or abandoned
Tex. Prop. Code Sec. 53.052(d)(opens the statute in a new tab)Someone else can shorten this windowThe owner's reserved funds: 30 days after the earliest of completion, termination or abandonment of the original contract (unless you gave a retainage notice)
Tex. Prop. Code Sec. 53.103(2)(opens the statute in a new tab)- File suit to enforce
469 days after you last furnish labor or materials
Tex. Prop. Code Secs. 53.052(a)(1),(b), 53.158(a)(opens the statute in a new tab)- Where it's filed
County Clerk of the county where the improvements are located
Tex. Prop. Code Sec. 53.052(e)(opens the statute in a new tab)
The rules as the statute states them. LienShield turns them into dates from your project's work dates. Residential and commercial are the private-project rules; public jobs follow separate bond rules, covered in the steps below.
Step by step
19 steps for a subcontractor in Texas.
Step 1: Find out who owns the property before you do anything else
Before you sign the contract, or the day you realize you are not getting paid.
Texas has three completely separate systems and they share almost nothing. Private property gets a mechanic's lien. State, city, county, school district and other public property cannot be liened at all — you claim against the general contractor's payment bond instead. Federal property is its own third system under federal law. Running the lien process on a public job produces a document that does nothing.
- Where it goes
- The county clerk's real property records will show the owner. On a public job, the governmental entity that awarded the contract holds the bond and must provide a copy.
- How
- Ask the general contractor who the owner is and whether there is a payment bond. On a Texas public job a payment bond is required when the prime contract exceeds $25,000, or exceeds $50,000 for a municipality or a Transportation Code ch. 22, subch. D joint board.
- Proof to keep
- A copy of the payment bond if there is one, and the name and address of the surety.
If you miss it: You spend your whole window perfecting the wrong remedy. A lien affidavit filed against public property is void, and by the time you find out, the bond-claim deadlines have usually run.
Step 2: Decide whether the job is residential or commercial
Before you calculate any deadline.
Every Texas deadline is one month shorter on a residential job. 'Residential' is narrower than it sounds: it means a single-family house, duplex, triplex or quadruplex, or a condominium or co-op unit, owned by one or more adults and used or intended as a dwelling by one of the owners. A five-unit-or-larger apartment complex is NOT residential — it gets the longer commercial deadlines.
- How
- Check the number of dwelling units and whether an owner lives there or intends to. If you are not certain, the safe move is to work the shorter residential calendar — it is never too early.
- Proof to keep
- Whatever you relied on: the contract description, the plans, the appraisal district record.
If you miss it: If you treat a residential job as commercial, every deadline you calculate is a full month too late and the lien is gone. Treating a commercial job as residential costs you nothing but time.
Step 3: On a homestead, make sure the owner's written contract was done right before work started
Before the first day of work. If you are already on the job, check the county records now.
A homestead is the one place in Texas where a lien can be dead before anyone does anything wrong. To fix a lien on a homestead, the original contractor's contract with the owner must be in writing, must be signed BEFORE any labor or material is furnished, must be signed by both spouses if the owner is married, and must be filed with the county clerk. If you are a subcontractor or supplier, you cannot fix this after the fact — the original contractor either did it or did not.
- Where it goes
- The county clerk of the county where the property is located.
- How
- The original contractor signs the contract with the owner, gets both spouses' signatures if the owner is married, and files it with the county clerk before work begins. Everyone else searches the county real property records for that recorded contract.
- Proof to keep
- A file-stamped copy of the recorded contract, or your search result showing it is not there.
What the document must contain
- A written contract between the owner and the original contractor
- Signed before any labor or materials are furnished
- Signed by both spouses if the owner is married
- Filed with the county clerk
If you miss it: There is no valid homestead lien for anyone — the original contractor or anyone below. It is an express ground for a court to strike the lien on a summary motion.
Step 4: Read your own contract for a lien waiver you already signed
Before you sign, and again before you spend money perfecting a lien.
Texas is unusual here. On a single-family house, townhouse or duplex (and related land development), a lien waiver written into the contract and signed BEFORE work begins is enforceable. In most states that waiver would be void. A residential contractor or sub may have signed away lien rights at contract signing without realizing it. The exception: this does not apply to someone who supplies only material and furnishes no labor.
- How
- Read the lien and waiver clauses in the written original contract or subcontract.
- Proof to keep
- The full signed contract, including exhibits and any incorporated general conditions.
If you miss it: You perfect a lien you already waived. The owner removes it on a summary motion, and you may face a demand to release it.
Step 5: Send a Notice of Claim for Unpaid Labor or Materials for EVERY unpaid month
Commercial job: by the 15th day of the THIRD month after the month you worked. June work is due September 15. Residential job: by the 15th day of the SECOND month after the month you worked. June work is due August 15. One notice per unpaid month, every month, until you are paid. If the 15th lands on a Saturday, Sunday or legal holiday, you get the next business day.
This is the step Texas contractors lose liens on. If you did not contract directly with the owner, you must send a separate notice for each and every month in which you furnished labor or materials and were not paid. A single notice covering six months of unpaid work, timed off the last month, protects only the months that are still open. The notice also lets the owner hold back money from the general contractor, which is often what actually gets you paid.
- Where it goes
- To BOTH the owner (or reputed owner) AND the original contractor. Both, every month. Missing one of the two recipients is the same as not sending it.
- How
- Hand it to the person, or send it by certified mail, or use any traceable private delivery service that can confirm proof of receipt. If you use certified mail, dropping it in the mail on time counts — you do not have to prove they received it.
- Proof to keep
- A copy of every notice, the certified mail receipt or delivery-service tracking for each one, and a running log of the date and method of each notice. You will have to restate those dates and methods inside the lien affidavit later, so keep them in one place.
What the document must contain
- The date of the notice
- A description of the project, enough to identify it
- Your name and address
- The type of labor or materials you furnished
- The name of the original contractor
- The name of the party you contracted with
- The amount of the claim
- The name and physical address of your contact person
- An invoice or billing statement may be included
If you miss it: You lose lien rights for that month's work. Not the whole lien necessarily — just every month you failed to notice, which on a long unpaid run is most of the money. It is the first listed ground for a court to strike the lien on a summary motion.
Step 6: Send a separate Notice of Claim for Unpaid Retainage
By the EARLIER of: 30 days after your own contract is completed, terminated or abandoned; or 30 days after the original contract is terminated or abandoned. Whichever comes first.
Retainage has its own notice with its own much shorter clock, and it is mandatory — without it your lien for unpaid retainage is not valid. The trap is the second half of the deadline: it also runs from the day the ORIGINAL contract is terminated or abandoned, which is something you often will not be told about. If the general contractor walks off in March, your 30 days started in March.
- Where it goes
- To BOTH the owner (or reputed owner) AND the original contractor.
- How
- Same delivery methods as the monthly notice — in person, certified mail, or a traceable private delivery service that can confirm proof of receipt.
- Proof to keep
- A copy of the notice plus certified mail or delivery-service proof, and whatever told you the original contract had ended.
What the document must contain
- A description of the project
- Your name
- The type of labor or materials you furnished
- The name of the original contractor
- The total amount of unpaid retainage
- Your contact information
If you miss it: Your lien for unpaid retainage is invalid. On most jobs the retainage is the remaining profit.
Step 7: File your lien affidavit — deadline runs from when YOUR work ended
Commercial job: by the 15th day of the FOURTH month after the later of the month you last furnished labor or materials, or the month specially fabricated material would normally have been delivered. Last work in June means October 15. Residential job: the 15th day of the THIRD month — last work in June means September 15. Weekend or legal holiday rolls to the next business day.
Your filing clock does not run from when the project finished. It runs from the month YOU last furnished labor or materials. If you finished in March and the building is completed in September, your clock started in March. Getting this backwards is how subcontractors file six months late.
- Where it goes
- The county clerk of the county where the improvements are located. If the clerk mis-records or mis-indexes it, that does not invalidate your lien.
- How
- File a sworn, notarized affidavit with the county clerk. The clerk records it and indexes it under the claimant, the original contractor and the owner. A recording fee applies and varies by county.
- Proof to keep
- The file-stamped copy showing the clerk's recording date and document number, and your receipt.
If you miss it: No lien. There is no extension and no cure.
Step 8: If you are claiming retainage, use the retainage filing deadline instead
By the 15th day of the THIRD month after the month the original contract you performed under was completed, terminated or abandoned. On a commercial job this is one month before the ordinary deadline in the previous step — do not use the fourth-month date for a retainage claim.
A lien claim for retainage has its own filing deadline, and on a commercial job it is a FULL MONTH EARLIER than the ordinary deadline. It also runs from a different event: the end of the ORIGINAL contract, not the end of your work. This deadline is the same on residential and commercial jobs.
- Where it goes
- The county clerk of the county where the improvements are located.
- How
- File the sworn affidavit with the county clerk, same as any lien affidavit.
- Proof to keep
- The file-stamped affidavit, plus documentation of when the original contract ended.
If you miss it: You lose the lien for the retainage — typically the largest single piece still owed.
Step 9: To reach the owner's 10 percent reserve, file within 30 days
Within 30 days after the EARLIEST of: the work is completed; the original contract is terminated; or the original contractor abandons the contract. The one relief valve: if you gave the retainage notice in the earlier step, Sec. 53.057(f) lets you file by the ordinary Sec. 53.052 date instead.
Texas requires the owner to hold back 10 percent of the contract price (or 10 percent of the value of the work) during the job and for 30 days after it is finished. That reserve is often the only pot of money a remote subcontractor can actually reach. To get a lien on it you must have sent the notices this chapter requires AND filed your affidavit within 30 days. This is the shortest deadline in the whole chapter, and it runs from whichever of three events happens FIRST.
- Where it goes
- The county clerk of the county where the improvements are located.
- How
- File the sworn affidavit with the county clerk.
- Proof to keep
- Your file-stamped affidavit, proof of every notice you sent, and whatever established the completion, termination or abandonment date.
If you miss it: You cannot reach the owner's reserved 10 percent. If the owner already followed Sec. 53.101 and paid the retainage out before you perfected, that is also an express ground to strike the lien.
Step 10: Put every required element in the affidavit
Before you take it to the notary.
The affidavit is a sworn document and the contents are set by statute. Two of the required elements were added in 2022 and are missing from most older forms: a statement of each month you worked, and a statement of the date and delivery method of every notice you sent the owner. If your form does not have those two fields, it is a pre-2022 form.
- How
- Sign it in front of a notary. It must be sworn — the statute requires a sworn statement of the amount claimed.
- Proof to keep
- A complete file-stamped copy with the notary jurat, plus the attachments you filed.
What the document must contain
- A sworn statement of the amount of the claim
- The name and last known address of the owner or reputed owner
- A general statement of the work done or materials furnished — and if you are not the original contractor, a statement of each month in which the work was done
- The name and last known address of the person who hired you
- The name and last known address of the original contractor
- A legally sufficient description of the property
- Your name, mailing address, and physical address if different
- If you are not the original contractor: a statement identifying the date each notice of the claim was sent to the owner and the method by which it was sent
- On a homestead: the notice in at least 10-point boldface reading NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN.
- Optional: attach the written contract and a copy of each notice you sent
If you miss it: An affidavit that does not comply with Sec. 53.054 is an express ground for a court to strike the lien on a summary motion, even if you filed on time.
Step 11: Send a copy of the filed affidavit within 5 days
Not later than the fifth day after the date the affidavit is filed with the county clerk.
This is the single most-missed step in Texas. You filed perfectly and on time, and the lien still comes off because nobody mailed the copy. It is its own express ground for removal.
- Where it goes
- To the owner or reputed owner at the owner's last known business or residence address. If you are not the original contractor, you must ALSO send a copy to the original contractor at their last known business or residence address, within the same five days.
- How
- In person, certified mail, or a traceable private delivery service that can confirm proof of receipt.
- Proof to keep
- Certified mail receipts or delivery tracking for each recipient, dated within five days of the file stamp. This is the proof that wins the removal hearing.
What the document must contain
- A complete copy of the filed affidavit as recorded
If you miss it: The owner can have your lien removed on a summary motion on this ground alone.
Step 12: Watch the county records for the owner's affidavit of completion
From the point the job winds down until your filing deadline passes. The owner must send you a copy if you already sent a notice under Sec. 53.056 or Sec. 53.057, or if you asked for one in writing — by the third day after filing, or the tenth day after receiving your lien notice, whichever is later.
This is a lever the owner can pull against you. The owner can record an affidavit of completion, and it becomes prima facie evidence of when the work was finished. That date is what your 30-day reserved-funds clock and an original contractor's filing clock run from. If the owner files it more than 10 days after actual completion, the FILING date becomes the completion date. Either way, the date of record can be earlier than the date you assumed, and your deadline moves up.
- Where it goes
- The county clerk of the county where the property is located.
- How
- Search the county clerk's real property records under the owner's name, or ask the clerk. Sending your monthly notices is also what puts you on the list of people the owner has to notify.
- Proof to keep
- A copy of any affidavit of completion you find or receive, with its recording date.
If you miss it: You calculate your deadline from a later completion date than the one of record and file late. There is no cure.
Step 13: Watch for a bond filed to indemnify against your lien
Any time after you file. The county clerk issues notice of the bond and mails you a copy by certified mail, using the address in your lien affidavit — which is a good reason to make sure your affidavit states your address.
A second lever. Anyone — usually the owner or the general contractor — can file a bond with the county clerk to indemnify against your lien. Once the bond is filed, notice is issued and both are recorded, your claim against the property is discharged. You are no longer suing the land; you are suing the bond. And the clock changes.
- Where it goes
- The bond is filed with the county clerk of the county where the property is located.
- How
- Once you receive notice, your suit goes against the bond. You may not sue on the bond later than one year after the date the notice is served, or after the date your underlying lien claim becomes unenforceable under Sec. 53.158 — whichever of those comes first.
- Proof to keep
- The notice of bond, the attached copy of the bond, and the date you received it.
If you miss it: The lien is discharged from the property and the shorter of the two bond clocks runs out. You are left with an ordinary breach-of-contract claim against whoever hired you.
Step 14: Respond if the other side moves to remove your lien
You must get at least 30 days' notice of the hearing, and the motion cannot be heard before the 30th day after you answer or appear.
Inside a foreclosure suit, the owner or another party can file a verified motion asking the court to remove your lien on any of seven statutory grounds — late notice, a defective or late affidavit, no copy sent within five days, expired retainage deadlines, funds deposited into the court's registry, a homestead defect, or a waiver you signed. You do not have to file a written response, but you do have to show up, and on two of those grounds the burden is on you.
- Where it goes
- The court where the foreclosure suit is pending.
- How
- You carry the burden of proving you sent the required notices and the copy of the affidavit in the time and manner the statute requires. The party moving to remove carries the burden on the other grounds.
- Proof to keep
- Everything from the earlier steps: every monthly notice with its certified mail receipt, the retainage notice, the file-stamped affidavit, and the five-day copy receipts. This hearing is decided on your paperwork.
If you miss it: The court signs an order removing the lien, and a certified copy of that order recorded in the county records discharges your lien unless a bond is filed within 30 days of the order.
Step 15: Sue to foreclose — the clock runs from the last day you COULD have filed
Not later than the first anniversary of the last day you could have filed the lien affidavit under Sec. 53.052. There is one extension: a written agreement with the then-current record owner, entered into BEFORE the year runs out, can push it to the second anniversary of the date you filed the affidavit — and that agreement has to be recorded in the same county where the lien is recorded.
This one catches careful people. Your year does not run from the day you recorded the lien. It runs from the last day you were allowed to file the affidavit. Filing early does not buy you extra time; it just means your year is already partly gone when you record.
- Where it goes
- District court. Foreclosure runs against the property in the county where it is located.
- How
- File a lawsuit to foreclose the lien.
- Proof to keep
- The file-stamped petition, and any recorded extension agreement.
If you miss it: The lien becomes unenforceable and is discharged of record. Suing later just to discharge the lien does not revive your right to foreclose. There is no cure.
Step 16: Public job: send the payment bond claim notices instead
Every bond beneficiary: mail notice to the prime contractor and the surety on or before the 15th day of the THIRD month after each month in which you performed labor or delivered material. If you have no direct contract with the prime contractor: ALSO mail notice to the prime on or before the 15th day of the SECOND month after each month you worked. If your subcontract provides for retainage, you owe a further notice to the prime on or before the 15th day of the second month after the date delivery or performance began. Specially fabricated material has its own second-month notice after the order is received and accepted.
On a state, city, county or school district job there is nothing to lien. You claim against the general contractor's payment bond, and the notices are monthly just like the private side — but they go to different people and follow a different calendar. If you are below the first tier, you owe TWO notices each month, not one.
- Where it goes
- To the prime contractor at its residence or last known business address. To the surety at the address on the bond or on the bond attachment, or the address on file with the Texas Department of Insurance.
- How
- Certified or registered mail — the public-works chapter does not allow the other delivery methods. The third-month notice to the prime and surety must be accompanied by a sworn statement of account confirming the amount is correct, that all known offsets, payments and credits are accounted for, and disclosing any retainage not yet due.
- Proof to keep
- Certified or registered mail receipts for every notice to every recipient, and a copy of each sworn statement of account. Note the MAILING date of each one — your suit deadline runs from it.
What the document must contain
- A sworn statement of account
- Confirmation that the claimed amount is correct and that known offsets, payments and credits are accounted for
- Disclosure of any retainage that is not yet due under the contract
If you miss it: You cannot recover on the bond for that month's work. Note one carve-out: the extra second-month notice under Sec. 2253.047 does not apply to an individual mechanic or laborer making a wage claim.
Step 17: Public job: sue on the payment bond within one year of MAILING your notice
You may sue once your claim has not been paid before the 61st day after the date you mailed the notice. You may NOT sue after the first anniversary of the date the claim notice was mailed. A suit on a performance bond has a different clock: not after the first anniversary of final completion, abandonment or termination of the public work contract.
The public-works suit clock is the one most people get wrong. It does not run from the end of the job. It runs from the date you mailed the claim notice — and because those notices are monthly, your earliest month expires first. If you started noticing in February, your February claim dies the following February, even if the job runs another year.
- Where it goes
- Court with jurisdiction; the chapter has its own venue provision.
- How
- File suit against the prime contractor and the surety.
- Proof to keep
- The certified or registered mail receipt for each notice, showing the mailing date. That date is your limitations anchor.
If you miss it: The bond claim for that month is barred. Because each month has its own anchor, you can lose the early months while the later ones are still alive.
Step 18: Small public contract with no bond: claim a lien on the contract funds
Give notice not later than the 15th day of the second month following the month in which the labor was performed or the material furnished.
If the public contract was too small to require a payment bond, there is no bond to claim against. Instead you can reach the money the governmental entity still owes the contractor. It is a lien on funds, not on property.
- Where it goes
- To the officials of the governmental entity holding the contract funds, and the contractor.
- How
- Give the notice the subchapter requires. If a bond is filed to release the claim, you must sue on that bond within six months after the bond is filed.
- Proof to keep
- Proof of mailing for each monthly notice, and the filing date of any release bond.
If you miss it: You lose the claim against the contract funds for that month, and there is no bond and no lien to fall back on.
Step 19: Federal job: give Miller Act notice within 90 days
Within 90 days from the date you last performed labor or last supplied material. Suit must be brought no later than one year after that same last day of labor or material.
On a federal construction project, Texas law does not apply at all. There is no lien and no state bond claim. The Miller Act governs, and unlike Texas it counts days, not months, and it counts from your last day of work rather than from the end of a month.
- Where it goes
- To the prime contractor that furnished the payment bond.
- How
- Written notice to the prime contractor, stating with substantial accuracy the amount claimed and the party you furnished the labor or material to. It has to be served in a way that provides written, third-party verification of delivery, or by a U.S. marshal.
- Proof to keep
- Third-party delivery verification, a copy of the notice, and dated records establishing your last day of labor or material.
If you miss it: If you had no direct contract with the prime contractor, you have no claim on the bond. A claimant who DID contract directly with the prime does not need this notice, but still has the one-year suit deadline.
Who can claim a lien in Texas
Who has a lien in Texas
- Has a lien: Anyone who labors on, or furnishes labor or materials for, the construction or repair of an improvement under a contract with the owner, the owner's agent, the original contractor, or a subcontractor (Tex. Prop. Code Sec. 53.021(a)(1)).
- Has a lien: Anyone who specially fabricates material for the job, even if the material was never delivered (Sec. 53.021(a)(2)).
- Has a lien: A licensed architect, engineer or surveyor who prepared a design, drawing, plan, plat, survey or specification for the work. Since 2022 they no longer need a contract with the owner (Sec. 53.021(a)(3)).
- Has a lien: A landscaper who furnishes labor, plant material or other supplies for landscaping an improvement, including retention ponds, retaining walls, berms, irrigation systems and fountains (Sec. 53.021(a)(4)).
- Has a lien: A demolition contractor who performs or furnishes labor or materials for demolishing an improvement (Sec. 53.021(a)(5)).
- Has a lien: Equipment rental companies: rental at reasonable rates counts as lienable 'material' when the equipment was delivered for use in directly performing the work (Sec. 53.001(4)).
Who does not have a lien in Texas
- No lien: Nobody can lien public property — state, city, county, school district or federal. On those jobs the remedy is a payment bond claim, not a lien (Tex. Gov't Code ch. 2253; 40 U.S.C. Sec. 3133).
Deadlines that can be cut short
In Texas, these events can start a shorter clock or end a window early. Most are in someone else's hands, and you may not hear about them for days, so watch your mail and the county records.
The original contract (the owner-to-original-contractor contract) is terminated or abandoned, whether or not the claimant's own subcontract is still running
Notice deadline: 30-day window
Tex. Prop. Code Sec. 53.057(a-1)(2)(opens the statute in a new tab)The owner records an affidavit of completion under Sec. 53.106
Notice deadline: shortened; the statute sets no fixed day count
Tex. Prop. Code Sec. 53.106(a),(b),(d)(opens the statute in a new tab)The original contract is completed, terminated or abandoned, where the claim or any part of it is for RETAINAGE
Lien filing deadline: 74-day window
Tex. Prop. Code Sec. 53.052(d)(opens the statute in a new tab)The EARLIEST of: completion of the work, termination of the original contract, or the original contractor's abandonment of performance under the original contract
Lien filing deadline: 30-day window
Tex. Prop. Code Sec. 53.103(2)(opens the statute in a new tab)The owner records an affidavit of completion under Sec. 53.106
Lien filing deadline: shortened; the statute sets no fixed day count
Tex. Prop. Code Sec. 53.106(a),(b),(d)(opens the statute in a new tab)Any person (in practice the owner or the original contractor) files a subchapter H bond to indemnify against the lien, the county clerk issues notice of the bond, and bond and notice are recorded
Time to sue: 365-day window
Tex. Prop. Code Secs. 53.171, 53.173, 53.174, 53.175(a)(opens the statute in a new tab)An objecting party files a verified summary motion to remove the lien under Sec. 53.160 and the court orders removal
Time to sue: 30-day window
Tex. Prop. Code Secs. 53.160, 53.161(b), 53.157(6)(opens the statute in a new tab)The original contractor or owner records a subchapter I bond to pay liens at the time the lien affidavit is filed
Time to sue: 365-day window
Tex. Prop. Code Sec. 53.208(a),(d)(opens the statute in a new tab)On small residential work subject to an enforceable prospective lien waiver, the owner or original contractor sends the claimant a written explanation of the basis for nonpayment, evidence of the contractual waiver of lien rights, and a notice of request for release of the lien
Time to sue: 14-day window
Tex. Prop. Code Sec. 53.282(a)(3),(b),(c)(opens the statute in a new tab)On a sub-threshold PUBLIC contract, the contractor files a bond to release a subchapter J lien on contract funds
Time to sue: 180-day window
Tex. Prop. Code Sec. 53.239(a)(opens the statute in a new tab)
Where you file
- Office
- County Clerk of the county where the improvements are located
- Recording fee
- $25–$60
- Notarization
- Required
- Sworn or verified
- Sworn affidavit
- How it is served
- Certified mail
- Copies
- 1
Fees and office procedures change; confirm them with the recording office before you file.
What trips people up in Texas
- Sending one notice at the end instead of one per month. A separate Notice of Claim is required for EACH month you furnished labor or materials and were not paid. A contractor with six unpaid months who sends one notice timed off the last month keeps that month and loses the other five. Any calculator that gives you a single pre-lien notice date for a Texas job is structurally wrong.
- Calculating your filing deadline from project completion. If you are not the contractor who signed with the owner, your clock runs from the month YOU last furnished labor or materials, not from when the building was finished. A sub who finished in March and waits for a September completion is roughly six months late.
- Treating retainage like the rest of the claim. Retainage has three separate shorter tracks: a 30-day notice, a filing deadline that on a commercial job is a full month earlier than the ordinary one, and a 30-day filing deadline to reach the owner's statutory 10 percent reserve. Two of those run from the end of the ORIGINAL contract, which is an event you often will not be told about.
- Assuming your year to sue starts when you record the lien. It starts on the last day you COULD have filed the affidavit. File two months early and you have ten months left, not twelve.
- Forgetting the five-day copy. A perfect, timely affidavit is removable on summary motion if the copy did not reach the owner — and the original contractor, if you are not the original contractor — within five days of filing. This is the most common way a valid Texas lien dies.
- Calling a five-unit apartment building or a build-to-rent project 'residential.' It is not. 'Residential' in Texas means a single-family house, duplex, triplex, quadruplex, or a condo or co-op unit used as a dwelling by an owner. Misclassifying a residential job as commercial gives you a calendar a full month too long and forfeits the lien.
- Working on a homestead without checking the owner's contract. If the original contractor did not sign a written contract with the owner before work began, signed by both spouses if the owner is married, and file it with the county clerk, there is no valid homestead lien for anyone below either. A subcontractor usually cannot discover this without searching the county records, and cannot fix it afterward.
- Signing away lien rights at contract signing on small residential work. In Texas a lien waiver in the written contract for a single-family house, townhouse or duplex, signed before work begins, is enforceable. Material-only suppliers are excepted. Most states void these waivers; Texas does not.
- Using a lien or notice form printed before 2022. H.B. 2237 repealed Secs. 53.053, 53.056(b)-(f), 53.057(b)-(e) and (g), 53.058, 53.081(d), 53.083, 53.158(b), 53.252 and 53.253 effective January 1, 2022. Any form, checklist or help text citing Sec. 53.252, Sec. 53.253, Sec. 53.056(b), a 'second month notice to the general contractor' on a commercial job, or a separate specially-fabricated-items notice is describing law that no longer exists. Pre-2022 forms also omit the two affidavit elements H.B. 2237 added: the statement of each month worked, and the statement of the date and method of each notice sent.
- The other direction of the same trap: H.B. 2237 applies only to an original contract entered into on or after January 1, 2022. If the original contract on your job predates that, prior law governs and the notice structure and suit window are different. Rare and shrinking, but real on long-running jobs.
- Missing the owner's affidavit of completion. Once recorded it is prima facie evidence of the completion date, and if it was filed more than 10 days after actual completion, the filing date becomes the completion date. That date drives the 30-day reserved-funds clock and an original contractor's filing clock. Assume a later completion date than the one of record and you file late.
- Ignoring a bond filed to indemnify against your lien. When that bond is filed, noticed and recorded, your claim against the property is discharged and you must sue on the bond within one year of service of the notice — or by the date your lien claim becomes unenforceable under Sec. 53.158, whichever is first.
- Running the private lien process on a public job. Public property cannot be liened. The recorded affidavit does nothing, and by the time you learn that, the Gov't Code ch. 2253 bond notice deadlines have usually passed. Public-works notices also require certified or registered mail specifically — the private-side delivery options do not apply.
- Design professionals, landscapers and demolition contractors assuming their lien relates back. It does not. The inception of a lien created under Sec. 53.021(3), (4) or (5) is the date the affidavit is recorded, so it sits behind every previously recorded deed of trust. A timely, valid lien in that category can still be economically worthless.
- Assuming the 15th is always the 15th. If a Chapter 53 deadline falls on a Saturday, Sunday or legal holiday, it moves to the next business day. That is a small gift, not a planning tool — but a checklist built on a pre-2025 rule that moved the date BACKWARD is wrong.
After you file
- Send the copy. Within five days of filing, get a copy of the recorded affidavit to the owner, and to the original contractor too if you are not the original contractor. Keep the certified mail receipts — this is the single most common ground for removal (Sec. 53.055; Sec. 53.160(b)(3)).
- Expect the owner to start withholding. Your notice under Sec. 53.056 or Sec. 53.057 authorizes the owner to hold back from the general contractor an amount sufficient to pay your claim. On a Sec. 53.056 notice the owner may withhold immediately on receipt; on a Sec. 53.057 retainage notice the owner may withhold on receipt of a copy of your affidavit. This is often what actually produces payment (Sec. 53.081).
- Keep sending monthly notices if you are still owed for later months. Filing a lien does not close out the notice obligation for months you have not yet noticed.
- Watch the county records. Two filings by the other side change your position: an owner's affidavit of completion, which can move your deadline up (Sec. 53.106), and a bond to indemnify against the lien, which discharges your claim against the property and replaces it with a claim on the bond (Secs. 53.171, 53.173, 53.175).
- Calendar the suit deadline from the last day you could have filed, not from the day you filed. If you need more time, a written extension must be agreed with the then-current record owner BEFORE the year runs out and must be recorded in the same county (Sec. 53.158(a), (a-2)).
- If you are served with a motion to remove the lien, you do not have to file a written response, but you must appear. You will carry the burden of proving you sent the required notices and the copy of the affidavit on time and in the required manner. The hearing cannot be held before the 30th day after you answer or appear, and you are entitled to at least 30 days' notice of it (Sec. 53.160).
- When you get paid, sign and record a release. A lien is discharged of record by a recorded release, by a recorded final judgment or court order, by a bond filed under Subchapter H or I, by a recorded order removing the lien under Sec. 53.160 with no bond filed within 30 days, or simply by your failure to sue in time (Sec. 53.157).
Where this comes from
Based on Tex. Prop. Code ch. 53, Secs. 53.001-53.287, as amended by H.B. 2237, 87th Leg. R.S. (2021), eff. Jan. 1, 2022, and S.B. 929, 89th Leg. R.S. (2025), eff. May 21, 2025; public works payment bonds: Tex. Gov't Code ch. 2253; federal projects: 40 U.S.C. Secs. 3131-3134 (Miller Act)(opens the statute in a new tab). Each step above links to the section it comes from.
Researched from the statute and independently cross-checked. Not yet reviewed by a licensed attorney. Last verified 2026-09-17.
This is general information about the lien process in this jurisdiction, not legal advice for your project. LienShield is a document preparation service, not a law firm. Verify with counsel before relying on any date or step.